Roosevelt July Progress

Construction Update
: July 2019

Project (1 or 2): Interim Housing

Construction Update: In June, site work began and was completed, and electrical work to connect the interim housing portables to power and data began. 

One Month Look Ahead: In July, electrical work to connect the portables to power and data will continue, and gates will be installed.


Project (2 or 2): Solar

Construction Update: In June, concrete pour began and was completed. 

One Month Look Ahead
: In July, steel erection will begin..


Immediate Impacts:

Roosevelt Power July Impact