McKinley Lunch Shelter Weekly Update

Posted by Ty Specht on 10/23/2017 11:50:00 AM

Weekly Construction Update: Week of October 23-27

Project: HVAC Upgrade

Description of Work: Construction company is digging to place underground utilities to include sewer and electrical lines.  Existing utilities are removed to install new.

One Week Schedule: The following site work will occur:  Concrete demolition and ground leveling.

Immediate Site Impacts:

  Y N   Nature of Impact      
Traffic   X    
Sound X     Loud demolition and heavy equipment noise.
Smell   X    
Power   X    
Classroom Impact X     Impacts the outdoor P.E. activities and recess.
After Hours work   X    
Weekend Work   X    
Weather Delay   X    

MIT Lunch Shelter