Fair Oaks Lunch Shelter Weekly Update

Posted by Ty Specht on 11/6/2017 8:00:00 AM

Weekly Construction Update: Week of November 6

Project: Lunch Shelter

Description of Work: General Contractor has completed grinding and leveling of the existing asphalt. Shade Structure contractor has cut holes in the asphalt to insert columns and footings for the shade structure.

One Week Schedule: Shade Structure Installer to drill holes and fill with concrete, set steel plates, columns, and grout this coming week.

Immediate Site Impacts:

  Y N   Nature of Impact      
Traffic   X    
Sound     Trucks and pouring.
Smell   X    
Power   X    
Classroom Impact   X    
After Hours work   X    
Weekend Work   X    
Weather Delay   X    