Mandarin Immersion Orion Alternative Monthly Construction Update September 2021

Mandarin Immersion Orion Alternative Monthly Construction Update September 2021

Posted by Brittney Bennett on 9/30/2021

Update: September 2021

Project (1 of 2): Interim Housing

Construction Update: This project was certified, and closeout is complete.

Project (2 of 2): Modernization and New Building

Construction Update: Ongoing CMU block punchlist at all wings. Metal decks at Wing 1 and Admin Wing have been completed. Ongoing metal studs at both floors of all wings. Fire sprinkler system installation completed at Wing 1 and nearing completion at Admin Wing. Ongoing plumbing and electrical rough-in at all wings. Second floor concrete slabs at Wing 1 and Admin Wing have been completed. Ongoing HVAC rough-in at Wing 2. Ongoing Wing 2 roof installation. Balcony concrete at Wing 2 has been completed. Liquid membrane nearing completion at all wings. Existing buildings modernization punchlist completion schedule pending school holiday.

One Month Look Ahead: Completion of CMU block punchlist at all wings. Completion of metal studs at both floors of all wings. Completion of fire sprinkler system installation at Admin Wing. Completion of plumbing and electrical rough-in at Wing 2 and ongoing at Wing 1 and Admin Wing. Completion of HVAC rough-in at Wing 2. Completion of Wing 2 roof installation and start of roof installation at Wing 1 and Admin Wing. Completion of liquid membrane at all wings. Wing 2 interior wall insulation to begin. Wing 2 metal lath to begin. Wing 2 storefront window frames to begin. Completion of elevator stairs and rails. Completion of punchlist for existing buildings modernization.