District Moves Quickly to Address Classroom Heat with Immediate and Long-Term Solutions

District Moves Quickly to Address Classroom Heat with Immediate and Long-Term Solutions

The Redwood City School District (RCSD) Board of Trustees is moving swiftly to address the absence of air conditioning in over 300 classrooms across the district. During the September 11, 2024, meeting, the Board received an update outlining both immediate and long-term solutions. Here’s a breakdown of the key developments:

Board Directive and Facilities Master Plan (FMP)

Board Directive: In the spring of 2024, the Board directed the Bond program management team to prioritize quick-start projects, focusing on cooling systems in classrooms without air conditioning.

Facilities Master Plan: For the first time in a decade, the district is updating its Facilities Master Plan (FMP) to reflect the changing needs of schools. One critical example is the increased demand for cooling systems due to rising temperatures driven by climate change.

Immediate Cooling Solutions

The district is implementing temporary heat-mitigation measures, including window film/tinting, though it's not compatible with all windows. In cases where tinting won't work, roller shades are being considered as an alternative. The facilities team is reviewing window types in the hottest classrooms to determine the best solution for each room.

The district is committed to rolling out these measures as fast as possible. “We’ve got to get the classrooms comfortable; the students can’t learn, and the teachers can’t teach,” Trustee Alisa MacAvoy emphasized.

Permanent Cooling Solutions

Permanent Plan: Construction of permanent HVAC systems are planned to begin in summer 2025, targeting the first group of schools. The permanent plan will involve substantial upgrades, including:

  • Enhancing electrical distribution systems at all campuses
  • Structural upgrades to support new systems
  • Fire alarm upgrades and new ductwork
  • The possibility of upgrades to the roof, depending on each school site

The estimated budget for each campus ranges from $5.5 million to $7 million.

Classroom Prioritization

The district will prioritize classrooms most in need, focusing on those with the hottest temperatures and classrooms that are most prepared for power upgrades. This targeted approach will ensure that relief is provided as quickly and effectively as possible.

Campus Matrix for Summer 2025 Construction:

The district will prioritize schools based on:

  • Readiness for electrical power system upgrades
  • Severity of classroom temperatures
  • Roofing and fire alarm conditions
  • Overall streamlining for quick implementation

Next Steps:

September 2024:

  • Planned roll-out of thermometers across campuses to monitor temperatures
  • Installation of temporary heat-mitigation measures begins

October 2024:

Final determination of the scope for Phase I of HVAC installations

November 2024 - January 2025:

HVAC design for Phase I schools will be integrated with the updated Facilities Master Plan and the district’s solar energy plan

Long-Term Commitment

This effort is part of Phase II of the district’s School Modernization and Construction Program, which is funded by Measure S as approved by voters in November of 2022.

RCSD remains committed to addressing current challenges, including climate change, while aligning facilities with modern educational needs. The district’s goal is to ensure that Redwood City schools provide safe, comfortable learning environments for students and staff, now and in the future.

Get Caught Up with Other Recent Hoover Updates:

Play and Pause Buttons for Slideshow
Following HVAC Upgrades and Lighting Improvements, District Begins Facilities Plan Implementation Talks

During the October 16 Board Study Session, the Board of Trustees presented three conceptual scenarios outlining possible approaches for implementing Measure S projects identified in the Facilities Master Plan (FMP). 

Read More about Following HVAC Upgrades and Lighting Improvements, District Begins Facilities Plan Implementation Talks
As Summer 2025 Approaches, District Advances Climate Control Projects Across Schools by Quickly Approving Final Steps for Implementation

The Board of Trustees approved multiple initiatives aimed at improving climate control in local schools. These measures are part of ongoing efforts to optimize learning conditions for students across the district, a priority identified early last fall.

Read More about As Summer 2025 Approaches, District Advances Climate Control Projects Across Schools by Quickly Approving Final Steps for Implementation
RCSD Board Approves Purchase of HVAC Equipment for First Phase Implementation

The first phase of installations will begin this summer at Adelante Selby, Hoover, Roosevelt, and Taft, as these schools require fewer structural and electrical modifications. The remaining campuses will receive upgrades in subsequent phases until every school is equipped with a modern HVAC system.

Read More about RCSD Board Approves Purchase of HVAC Equipment for First Phase Implementation
School Board Hears Audit Results: 2015 Measure T and 2022 Measure S Bond Funds

The performance audit revealed a positive assessment of the district's management, with no significant problems or disagreements identified. Spending on bond projects was found to align with what voters approved, ensuring accountability and transparency. Additionally, the audit confirmed that payroll and procurement procedures adhere to legal requirements, and no significant accounting issues or unreported financial problems were discovered. Overall, the audit concluded that the bond funds are well-managed and used appropriately.

Read More about School Board Hears Audit Results: 2015 Measure T and 2022 Measure S Bond Funds