Adelante Selby Spanish Immersion School

Program Management Team: Brailsford and Dunlavey | RGMK & Associates

 

Status: Interim Housing Construction

Contact Us: Don Dias

Other Project Details: 

Welcome to the Adelante Selby Spanish Immersion School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.

We thank you for your support of this bond and its associated projects.

Posted by Brittney Bennett on 5/31/2021

Update: May 2021

 

Project (1 of 4): Parking Lot Expansion

Construction Update: Project is completed and DSA certified.

 

Project (2 of 4): Solar

Construction Update: Project is completed and energized, producing power.

 

Project (3 of 4): Electric Vehicle Charging Stations

Construction Update: Project is completed and DSA certified.

 

Project (4 of 4): Modernization

Construction Update: Project is completed. DSA close out is ongoing, and certification is pending.

One Month Look Ahead: Pending DSA certification.

Posted by Brittney Bennett on 4/30/2021

Update: April 2021

 

Project (1 of 4): Parking Lot Expansion

Construction Update: Project is completed and DSA certified.

 

Project (2 of 4): Solar

Construction Update: Project is completed and energized, producing power.

 

Project (3 of 4): Electric Vehicle Charging Stations

Construction Update: Project is completed and DSA certified.

 

Project (4 of 4): Modernization

Construction Update: Project is completed. DSA close out is ongoing, and certification is pending.

One Month Look Ahead: Pending DSA certification.

Posted by Brittney Bennett on 3/31/2021

Update: March 2021

 

Project (1 of 4): Parking Lot Expansion

Construction Update: Project is completed and DSA certified.

 

Project (2 of 4): Solar

Construction Update: Project is completed and energized, producing power.

 

Project (3 of 4): Electric Vehicle Charging Stations

Construction Update: Project is completed and DSA certified.

 

Project (4 of 4): Modernization

Construction Update: Project is completed. DSA close out is ongoing and certification is pending.

One Month Look Ahead: Pending DSA certification.

Posted by Brittney Bennett on 2/26/2021

Update: February 2021

 

Project (1 of 4): Parking Lot Expansion

Construction Update: Project is completed and DSA certified.

 

Project (2 of 4): Solar

Construction Update: Project is completed and energized, producing power.

 

Project (3 of 4): Electric Vehicle Charging Stations

Construction Update: Project is completed and DSA certified.

 

Project (4 of 4): Modernization

Construction Update: Project is completed. DSA close out is ongoing and certification is pending

One Month Look Ahead: Pending DSA certification

Posted by Brittney Bennett on 1/27/2021

Update: January 2021

 

Project (1 of 4): Parking Lot Expansion

Construction Update: Project is completed and DSA certified.

 

Project (2 of 4): Solar

Construction Update: Project is completed and energized, producing power

 

Project (3 of 4): Electric Vehicle Charging Stations

Construction Update: Project is completed and DSA certified

 

Project (4 of 4): Modernization

Construction Update: Final punch walk performed, and punch walk items listed to be finalized and completed.

One Month Look Ahead: In February, project close-out and training are ongoing; and submittal of DSA documents for certification is ongoing. Roller shades install and modernization doors, including hardware to be completed.