Adelante Selby Spanish Immersion School
Program Management Team: Brailsford and Dunlavey | RGMK & Associates
Status: Interim Housing Construction
Contact Us: Don Dias
Other Project Details:
Welcome to the Adelante Selby Spanish Immersion School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.
We thank you for your support of this bond and its associated projects.
Posted by Brittney Bennett on 5/31/2021
Update: May 2021
Project (1 of 4): Parking Lot Expansion
Construction Update: Project is completed and DSA certified.
Project (2 of 4): Solar
Construction Update: Project is completed and energized, producing power.
Project (3 of 4): Electric Vehicle Charging Stations
Construction Update: Project is completed and DSA certified.
Project (4 of 4): Modernization
Construction Update: Project is completed. DSA close out is ongoing, and certification is pending.
One Month Look Ahead: Pending DSA certification.
Posted by Brittney Bennett on 4/30/2021
Update: April 2021
Project (1 of 4): Parking Lot Expansion
Construction Update: Project is completed and DSA certified.
Project (2 of 4): Solar
Construction Update: Project is completed and energized, producing power.
Project (3 of 4): Electric Vehicle Charging Stations
Construction Update: Project is completed and DSA certified.
Project (4 of 4): Modernization
Construction Update: Project is completed. DSA close out is ongoing, and certification is pending.
One Month Look Ahead: Pending DSA certification.
Posted by Brittney Bennett on 3/31/2021
Update: March 2021
Project (1 of 4): Parking Lot Expansion
Construction Update: Project is completed and DSA certified.
Project (2 of 4): Solar
Construction Update: Project is completed and energized, producing power.
Project (3 of 4): Electric Vehicle Charging Stations
Construction Update: Project is completed and DSA certified.
Project (4 of 4): Modernization
Construction Update: Project is completed. DSA close out is ongoing and certification is pending.
One Month Look Ahead: Pending DSA certification.
Posted by Brittney Bennett on 2/26/2021
Update: February 2021
Project (1 of 4): Parking Lot Expansion
Construction Update: Project is completed and DSA certified.
Project (2 of 4): Solar
Construction Update: Project is completed and energized, producing power.
Project (3 of 4): Electric Vehicle Charging Stations
Construction Update: Project is completed and DSA certified.
Project (4 of 4): Modernization
Construction Update: Project is completed. DSA close out is ongoing and certification is pending
One Month Look Ahead: Pending DSA certification
Posted by Brittney Bennett on 1/27/2021
Update: January 2021
Project (1 of 4): Parking Lot Expansion
Construction Update: Project is completed and DSA certified.
Project (2 of 4): Solar
Construction Update: Project is completed and energized, producing power
Project (3 of 4): Electric Vehicle Charging Stations
Construction Update: Project is completed and DSA certified
Project (4 of 4): Modernization
Construction Update: Final punch walk performed, and punch walk items listed to be finalized and completed.
One Month Look Ahead: In February, project close-out and training are ongoing; and submittal of DSA documents for certification is ongoing. Roller shades install and modernization doors, including hardware to be completed.