•  Selby
     
     
    Program Management Team: Brailsford and Dunlavey | RGM & AssociatesB&D      RGM   
     
    Status: Interim Housing Construction
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the Selby Lane Elementary School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

    Phase: Construction

     

     

  • Selby Lane Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 7:15:00 AM

    Selby Lane Progress Photo

     

    Update: August

    Project (1 of 3): Parking Lot Expansion

    Construction Update: In July, fencing and asphalt placement began.

    One Month Look Ahead: In August, the parking lot will be striped, and fencing and gate installation will continue.

     

    Project (2 of 3): Solar

    Construction Update: In July, the canopy system installation was completed.

    One Month Look Ahead: In August, electrical interconnection is scheduled.

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In July, substantial infrastructure was completed.

    One Month Look Ahead: The project is on track for completion by the end of August.

     

    Immediate Impacts:
    Selby Lane Traffic Sound Impacts August  

    Comments (-1)
  • Selby Lane Monthly Construction Update

    Posted by Neta Miller on 7/5/2019 7:00:00 AM

    Construction Update: July 2019

    Project (1 of 2): Parking Lot Expansion

    Construction Update: In June, site work began  including the demolition of asphalts and grating, and select existing fencing were removed.

    One Month Look Ahead: In July, fencing and gate installation will begin, and site work will continue pending solar installation.

     

    Project (2 of 2): Solar

    Construction Update: In June, directional boring underground and concrete pouring were completed. 

    One Month Look Ahead: In July, steel erection, module installation and electrical scope will begin.

     

    Immediate Impacts: 

    Selby Lane Traffic Sound July Impacts

    Comments (-1)
  • Selby Lane Monthly Construction Update

    Posted by Neta Miller on 6/7/2019 7:05:00 AM

    Construction Update: June 2019

    Project: Parking Lot Expansion

    Construction Update: In May, mobilization and demolition began at the existing parking lot areas that will be refinished.

    One Month Look Ahead: In June, construction is expected to include the demolition of the existing parking lot areas, and the start of soil backfilling and repaving preparations.

    Immediate Impacts:
    Selby Lane June Impacts

    Comments (-1)
  • Selby Lane April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 PM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more educational opportunities for the future leaders of our community.

     

    In 2017-18 Selby Lane School received HVAC system upgrades, lunch tables and umbrellas, and the Modernization and Parking Lot projects went through Schematic Design, Design Development, and Construction Document phases.

     

    The Selby Lane Modernization project was submitted to the Division of the State Architect (DSA) in December 2018, and the Parking Lot project was submitted in November 2018. DSA is a government body that provides design and construction oversight for K-12 schools, and will review Selby Lane’s Modernization and Parking Lot Construction Documents for compliance and accessibility.

     

    The scope of work submitted to DSA for Selby Lane Modernization includes, and is not limited to, the following:

    • Reconfigure administration space
    • New kitchen equipment
    • New parking lot and concrete walkways
    • Slurry coat and stripe existing paving
    • Exterior patch and paint
    • Selective flooring
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Security camera installation
    • Classroom technology package (includes Redcat Access classroom voice enhancement system and flat screen TVs on motorized, adjustable carts)

     

    The Selby Lane Modernization project is expected to complete DSA review in Summer 2019.

     

    The scope of work submitted to DSA for Selby Lane Parking Lot includes, and is not limited to, the following:

    • New parking lot and concrete walkways
    • Slurry coat and stripe existing paving

     

    The Selby Lane Parking Lot project is expected to complete DSA review in Spring 2019. All scope is subject to change.

     

    Selby Lane has two additional projects underway: a Solar Panel project and an Electric Vehicle (EV) Charging Stations project. The EV Charging Stations design is currently 50% complete.

     

    The Solar Panel construction is currently expected to begin in June 2019 and to be completed by October 2019, dates subject to change.

     

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Selby Lane Design Update

    Posted by Neta Assaf on 9/30/2018 6:00:00 AM

    Another summer full of fun (and work) has come and gone at Selby Lane School! Welcome back, we hope your school year is successful. The Bond Team is propelling the Measure T Bond Measure’s vision into reality. The design and construction process is being carefully guided, with everyone focused on making the Redwood City School District (RCSD) the best place for learning and exploration it can be.

     

    After the successful replacement of the previous air handling units with new Heating, Ventilation and Air Conditioning units at all second floor classrooms in March, 2018, Selby Lane has been full of activity:

    • A Construction-Related Testing and Inspection Agreement with Ninyo and Moore was approved by the Board.
    • Responses to the Request for Proposals for the Prop 39 Solar Project have been received, and the Board has approved REC Solar.
    • The team received the Schematic Design set for Selby Lane, which determines the project requirements and goals.
    • The team received the Design Development set for Selby Lane, which expands on Schematic Design, finalizing the design, specific building materials, and engages additional design experts (i.e. structural, mechanical, and landscape engineers).
    • Pre-construction work is underway to upgrade the sites electrical and gas services. This design process is underway and expected to commence during summer break 2019.
    • The team received a 50% Construction Documents notice – this phase will produce drawings with greater detail which will be used during construction.

     

    Next steps for the Selby Lane project include concluding the Construction Documents phase, followed by submission to the Division of the State Architect (DSA). Once DSA sign off has been received, Selby Lane will go into the bidding and construction phases.

     

    The Bond Team is happy to share that the timeline for completing all RCSD school site projects has been shortened to five years instead of the previously expected seven. Construction on some District sites is expected to begin as early as the start of 2019.

     

    For further information and inquiry, please contact Don Dias.

    Comments (-1)
  • Selby Lane - HVAC Weekly Update

    Posted by Ty Specht on 11/6/2017 7:00:00 AM

    Weekly Construction Update: Week of October 30 - November 3

    Project: HVAC Upgrade

    Description of Work: General Contractor has installed all mechanical units, including the air conditioning units in the 2nd-floor hallway. Pressure testing was done last week and the controls testing is ongoing. Final inspection of the project is scheduled for two weeks.

    One Week Schedule: Contractor will be installing and painting pipe wall enclosures as well as installing fence posts. Major construction is complete and the work is on track to be complete by the end of November.

    Immediate Site Impacts:

      Y N   Nature of Impact        
    Traffic   X    
    Sound   X    
    Smell   X    
    Classroom Impact   X    
    After Hours work     Work done to minimize school impact.
    Weekend Work   X    
    Weather Delay   X    

     

    Comments (-1)
  • Selby Lane - HVAC Weekly Update

    Posted by Ty Specht on 10/23/2017

    Weekly Construction Update: Week of October 30 - November 3

    Project: HVAC Upgrade

    Description of Work: General Contractor continutes installation of heating and cooling units at Selby Lane.

    One Week Schedule: Work is nearly completed at Selby Lane. The contractor will be enclosing the exterior units near student play areas with fencing. The contractor will be placing covers over exterior pipes and painting the covers to match the school.

    Immediate Site Impacts:

      Y N   Nature of Impact        
    Traffic   X    
    Sound   X    
    Smell   X    
    Classroom Impact   X    
    After Hours work   X    
    Weekend Work   X    
    Weather Delay   X    

     

    Comments (-1)
  • Selby Lane - HVAC Weekly Update

    Posted by Ty Specht on 10/19/2017 9:50:00 AM

    Weekly Construction Update: Week of October 23-27

    Project: HVAC Upgrade

    Description of Work: Contractor has completed the installation of most mechanical equipment in the classrooms. The exterior mechanical equipment installation will be complete by end of this week.

    One Week Schedule: The contractor is making final electric and gas connections in preparation to turn on the air conditioning units next week.

    Immediate Site Impacts:

      Y N   Nature of Impact        
    Traffic   X    
    Sound   X    
    Smell   X    
    Classroom Impact   X    
    After Hours work X      
    Weekend Work   X    
    Weather Delay   X    

    Selby HVAC

    Comments (-1)
  • Selby Lane Air Conditioning Schedule Update

    Posted by Ty Specht on 8/22/2017 12:00:00 PM

    To the Communities of Roy Cloud, Clifford, and Selby Lane Schools,

     

    On August 16, 2017 Board of Education approved the Heating, Ventilation, and Air Conditioning (HVAC) upgrades project, a second time. The new Contractor, O.C. McDonald, was sent the Notice of Award on August 17, 2017 and has 7 days to submit all the legal paperwork, including the schedule to the Bond Program Team. O.C. McDonald has been very proactive and intends to have all documents to the team as quickly as possible. At that time, the Bond Program Team will update the community on the dates that O.C. McDonald will be working, off school hours, at your sites.

     

    Unfortunately, due to circumstances outside the control of the Bond Team, the first contractor was unable to meet the contractual requirements of the project after being awarded. This forced the Bond Program Team to re-bid the HVAC projects which takes a minimum of five weeks starting with Board Approval to re-bid, placing us where we are today.

     

    As disappointing as the delay is to everyone, we choose to look at the positives. We have a better, more experienced contractor, and the projects came in on budget.

     

    Have a great year and we will publish the schedule soon.

     

    Regards,

    The Measure T Bond Program Team

    Comments (-1)
  • Selby Lane Conceptual Design

    Posted by Ty Specht on 8/17/2017 9:45:00 AM

    There are multiple phases of design that your school will progress through over the next several month. Those phases include:

     

    • Conceptual Design
    • Schematic Design
    • Design Development
    • Construction Documents
    •  

    A critical part of every project is the budget and ensuring that the design maximizes the budget. The architect of your school was provided a set budget and a design objective based on the goals of the Master Facility Plan and the board approved Gap Analysis finding. The attached document reflects the architect’s conceptual design for your site. Conceptual designs can be considered the first drawings that outline desires and opportunities. The level of detail is limited in this phase. The next phase, schematic development, will show addition details like wall locations, doors, and windows.

     

    The Bond Program Team is in constant contact with the school principal to confirm design developments through the entire process for feedback and design confirmation.

     

    Conceptual Design

    Comments (-1)