•  
     
     
    Program Management Team: Brailsford and Dunlavey | RGMK & AssociatesB&D      RGM   
     
    Status: Interim Housing Construction
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the Adelante Selby Spanish Immersion School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

    Phase: Construction

     

     

  • Adelante Modernization Monthly Construction Update

    Posted by Neta Miller on 1/9/2020 1:00:00 PM

    Update: December 2019

     

    Project (1 of 3): Parking Lot Expansion

    Construction Update: In December, closeout proceedings continued.

    One Month Look Ahead: In January, closeout proceedings are expected to be completed. 

     

    Project (3 of 3): Electric Vehicle Charging

    Construction Update: In December, this project was already completed and is in closeout. One Month Look Ahead: In January, this project will be in closeout.

    Comments (-1)
  • Adelante Selby Monthly Construction Update

    Posted by Neta Miller on 11/5/2019 3:10:00 PM

    Update: November 2019

     

    Project (1 of 3): Parking Lot Expansion

    Construction Update: In October, punch list items were completed.

    One Month Look Ahead: In November, this project will be in closeout.

     

    Project (2 of 3): Solar

    Construction Update: In October, this project was completed.

    One Month Look Ahead: In November, this project will be in closeout.

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In October, this project was completed.

    One Month Look Ahead: In November, this project will be in closeout.

     

    Comments (-1)
  • Adelante Selby Monthly Construction Update

    Posted by Neta Miller on 10/10/2019 3:00:00 PM

    Update: October 2019

     

    Project (1 of 3): Parking Lot Expansion

    Construction Update: In September, punch list item work began.

    One Month Look Ahead: In October, punch list items will continue.

     

    Project (2 of 3): Solar
    Construction Update: In September, the solar system has been energized and is producing power, and close out began.

    One Month Look Ahead: In October, close out will continue.

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In September, installation of the chargers began.

    One Month Look Ahead: In October, installation of the chargers will continue.

    Comments (-1)
  • Adelante Selby Summer 2019 Update

    Posted by Neta Miller on 9/12/2019 3:10:00 PM

    Welcome back to another beautiful school year! The Bond Team has been busy all summer, bringing the Measure T Bond Measure to life. From construction to design progress, the Bond Program is well on its way to transform and modernize the Redwood City School District.

     

    This summer, the district was full of construction:

    • 30 interim housing units were installed for use at the start of the 2019/20 school year
    • Eleven schools had active construction on their campus
    • Five school Modernization projects mobilized
    • Four solar projects mobilized
    • Four Electric Vehicle Charging projects mobilized

     

    Adelante Selby Elementary School saw the following progress:

    • Parking Lot Expansion is complete
    • 14 Electric Vehicle Charging station infrastructure substantially completed
    • Electric Vehicle Charging station infrastructure substantially completed
    • Electric Vehicle Charger installation began
    • Solar project canopy system fully installed
    • Solar project electrical interconnection completed
    • Bond Team partnered with PG&E to work on energizing the new Solar system to produce power

     

    Adelante Selby Solar

    Currently, the Adelante Selby Modernization scope is under review by the Division of the State Architect (DSA). DSA is a government body that provides design and construction oversight for K-12 school, and once the Bond Team receives DSA sign-off, procurement for construction will begin.

     

    The District and the Bond Team look forward to continued progress on campus and across the district, and to serving our community. Everyone is working hard to make the Redwood City School District the best learning environment it can be!

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Adelante Selby Construction Update

    Posted by Neta Miller on 9/4/2019 7:35:00 AM

    Update: September 2019

     

    Project (1 of 3): Parking Lot Expansion

    Construction Update: In August, the parking lot expansion was completed, and fencing and gate installed.

    One Month Look Ahead: In September, punch list item work will begin.

     

    Project (2 of 3): Solar

    Construction Update: In August, the solar system was brought online and began producing power.

    One Month Look Ahead: In September, punch list items will begin.

     

    Project: Electric Vehicle Charging Stations

    Construction Update: In August, infrastructure and concrete bases were completed.

    One Month Look Ahead: In September, installation of the charger will begin.

    Comments (-1)
  • Selby Lane Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 7:15:00 AM

    Selby Lane Progress Photo

     

    Update: August

    Project (1 of 3): Parking Lot Expansion

    Construction Update: In July, fencing and asphalt placement began.

    One Month Look Ahead: In August, the parking lot will be striped, and fencing and gate installation will continue.

     

    Project (2 of 3): Solar

    Construction Update: In July, the canopy system installation was completed.

    One Month Look Ahead: In August, electrical interconnection is scheduled.

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In July, substantial infrastructure was completed.

    One Month Look Ahead: The project is on track for completion by the end of August.

     

    Immediate Impacts:
    Selby Lane Traffic Sound Impacts August  

    Comments (-1)
  • Selby Lane Monthly Construction Update

    Posted by Neta Miller on 7/5/2019 7:00:00 AM

    Construction Update: July 2019

    Project (1 of 2): Parking Lot Expansion

    Construction Update: In June, site work began  including the demolition of asphalts and grating, and select existing fencing were removed.

    One Month Look Ahead: In July, fencing and gate installation will begin, and site work will continue pending solar installation.

     

    Project (2 of 2): Solar

    Construction Update: In June, directional boring underground and concrete pouring were completed. 

    One Month Look Ahead: In July, steel erection, module installation and electrical scope will begin.

     

    Immediate Impacts: 

    Selby Lane Traffic Sound July Impacts

    Comments (-1)
  • Selby Lane Monthly Construction Update

    Posted by Neta Miller on 6/7/2019 7:05:00 AM

    Construction Update: June 2019

    Project: Parking Lot Expansion

    Construction Update: In May, mobilization and demolition began at the existing parking lot areas that will be refinished.

    One Month Look Ahead: In June, construction is expected to include the demolition of the existing parking lot areas, and the start of soil backfilling and repaving preparations.

    Immediate Impacts:
    Selby Lane June Impacts

    Comments (-1)
  • Selby Lane April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 PM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more educational opportunities for the future leaders of our community.

     

    In 2017-18 Selby Lane School received HVAC system upgrades, lunch tables and umbrellas, and the Modernization and Parking Lot projects went through Schematic Design, Design Development, and Construction Document phases.

     

    The Selby Lane Modernization project was submitted to the Division of the State Architect (DSA) in December 2018, and the Parking Lot project was submitted in November 2018. DSA is a government body that provides design and construction oversight for K-12 schools, and will review Selby Lane’s Modernization and Parking Lot Construction Documents for compliance and accessibility.

     

    The scope of work submitted to DSA for Selby Lane Modernization includes, and is not limited to, the following:

    • Reconfigure administration space
    • New kitchen equipment
    • New parking lot and concrete walkways
    • Slurry coat and stripe existing paving
    • Exterior patch and paint
    • Selective flooring
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Security camera installation
    • Classroom technology package (includes Redcat Access classroom voice enhancement system and flat screen TVs on motorized, adjustable carts)

     

    The Selby Lane Modernization project is expected to complete DSA review in Summer 2019.

     

    The scope of work submitted to DSA for Selby Lane Parking Lot includes, and is not limited to, the following:

    • New parking lot and concrete walkways
    • Slurry coat and stripe existing paving

     

    The Selby Lane Parking Lot project is expected to complete DSA review in Spring 2019. All scope is subject to change.

     

    Selby Lane has two additional projects underway: a Solar Panel project and an Electric Vehicle (EV) Charging Stations project. The EV Charging Stations design is currently 50% complete.

     

    The Solar Panel construction is currently expected to begin in June 2019 and to be completed by October 2019, dates subject to change.

     

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Selby Lane Design Update

    Posted by Neta Assaf on 9/30/2018 6:00:00 AM

    Another summer full of fun (and work) has come and gone at Selby Lane School! Welcome back, we hope your school year is successful. The Bond Team is propelling the Measure T Bond Measure’s vision into reality. The design and construction process is being carefully guided, with everyone focused on making the Redwood City School District (RCSD) the best place for learning and exploration it can be.

     

    After the successful replacement of the previous air handling units with new Heating, Ventilation and Air Conditioning units at all second floor classrooms in March, 2018, Selby Lane has been full of activity:

    • A Construction-Related Testing and Inspection Agreement with Ninyo and Moore was approved by the Board.
    • Responses to the Request for Proposals for the Prop 39 Solar Project have been received, and the Board has approved REC Solar.
    • The team received the Schematic Design set for Selby Lane, which determines the project requirements and goals.
    • The team received the Design Development set for Selby Lane, which expands on Schematic Design, finalizing the design, specific building materials, and engages additional design experts (i.e. structural, mechanical, and landscape engineers).
    • Pre-construction work is underway to upgrade the sites electrical and gas services. This design process is underway and expected to commence during summer break 2019.
    • The team received a 50% Construction Documents notice – this phase will produce drawings with greater detail which will be used during construction.

     

    Next steps for the Selby Lane project include concluding the Construction Documents phase, followed by submission to the Division of the State Architect (DSA). Once DSA sign off has been received, Selby Lane will go into the bidding and construction phases.

     

    The Bond Team is happy to share that the timeline for completing all RCSD school site projects has been shortened to five years instead of the previously expected seven. Construction on some District sites is expected to begin as early as the start of 2019.

     

    For further information and inquiry, please contact Don Dias.

    Comments (-1)