    Program Management Team: Brailsford and Dunlavey | RGMK & AssociatesB&D      RGM   
     
    Status: DSA Review
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the Roosevelt Elementary School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by CAW Architects with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     Progress Map

     
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 2/5/2020 8:10:00 AM

    Update: February 2019

     

    Project (1 of 2): Interim Housing

    Construction Update: In January, the closeout and punch list began.

    One Month Look Ahead: In February, the punch list is expected to be completed, and closeout will begin.

     

    Project (2 of 2): Solar

    Construction Update: This project is substantially complete and energized.

    Comments (-1)
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 12/6/2019 4:10:00 PM

    Update: December 2019

     

    Project (1 of 2): Interim Housing
    Construction Update: In November, electrical work was on hold, awaiting PG&E interconnection.
    One Month Look Ahead: In December, PG&E interconnection is expected and closeout will begin.

     

    Project (2 of 2): Solar
    Construction Update: In December, PG&E transformer installation is required.

    Comments (-1)
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 11/5/2019 3:05:00 PM

    Update: November 2019

     

    Project (1 of 2): Interim Housing

    Construction Update: Electrical work is underway, pending PG&E interconnection.

     

    Project (2 of 2): Electric Vehicle Charging Stations

    Construction Update: In October, this project was online and the Bond Team is working with PG&E to upgrade the electrical service to allow for full energization.

    One Month Look Ahead: In November, the Bond Team will continue to work with PG&E to fully energize the panels.

    Comments (-1)
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 10/10/2019 3:00:00 PM

    Update: October 2019

     

    Project (1 of 2): Interim Housing

    Construction Update: The interim housing portables are in full use.

     

    Project (2 of 2): Solar

    Construction Update: In September, installation continued.

    One Month Look Ahead: In October, transformer installation is expected.

     

    Roosevelt Solar September

     

    Roosevelt Interim Housing September

    Comments (-1)
  • Roosevelt Summer 2019 Update

    Posted by Neta Miller on 9/12/2019 4:05:00 PM

    Welcome back to another beautiful school year! The Bond Team has been busy all summer, bringing the Measure T Bond Measure to life. From construction to design progress, the Bond Program is well on its way to transform and modernize the Redwood City School District.

     

    This summer, the district was full of construction:

    • 30 interim housing units were installed for use at the start of the 2019/20 school year
    • Eleven schools had active construction on their campus
    • Five school Modernization projects mobilized
    • Four solar projects mobilized
    • Four Electric Vehicle Charging projects mobilized

     

    Roosevelt Elementary School saw the following progress:

    • Six Interim Housing Units installed
    • All Interim Housing Units were connected for power and data
    • Solar project canopy system fully installed
    • Solar project electrical interconnection completed
    • Bond Team partnered with PG&E to work on energizing the new Solar system to produce power

     

    Roosevelt Solar

     

    Currently, the Roosevelt Modernization scope is under review by the Division of the State Architect (DSA). DSA is a government body that provides design and construction oversight for K-12 school, and once the Bond Team receives DSA sign-off, procurement for construction will begin.

     

    The District and the Bond Team look forward to continued progress on campus and across the district, and to serving our community. Everyone is working hard to make the Redwood City School District the best learning environment it can be!

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 9/4/2019 7:05:00 AM

    Update: September 2019

     

    Project (1 of 2): Interim Housing

    Construction Update: In August, site work was completed.

    One Month Look Ahead: In September, electrical work to connect the interim housing portables to power and data will be completed.

     

    Project (2 of 2): Solar

    Construction Update: In August, the solar system was brought online.

    One Month Look Ahead: In September, the Bond Team will collaborate with PG&E to upgrade the transformer.

    Comments (-1)
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 6:35:00 AM

    Roosevelt Progress Photo

     

    Roosevelt Progress Photo

     

    Update: August 2019

    Project (1 of 2): Interim Housing

    Construction Update: In July, electrical work to connect the interim housing portables to power and data continued.

    One Month Look Ahead: In August, electrical work will be completed, and the punch list walk will be conducted.

     

    Project (2 of 2): Solar

    Construction Update: In July, the canopy system installation and electrical interconnection were completed.

    One Month Look Ahead: In August, installation work will continue.

     

    Immediate Impacts:
    Roosevelt No August Impacts

    Comments (-1)
  • Roosevelt Monthly construction Update

    Posted by Karen Summerville on 7/5/2019 7:00:00 AM

    Roosevelt July Progress

    Construction Update
    : July 2019

    Project (1 or 2): Interim Housing

    Construction Update: In June, site work began and was completed, and electrical work to connect the interim housing portables to power and data began. 

    One Month Look Ahead: In July, electrical work to connect the portables to power and data will continue, and gates will be installed.


    Project (2 or 2): Solar

    Construction Update: In June, concrete pour began and was completed. 

    One Month Look Ahead
    : In July, steel erection will begin..


    Immediate Impacts:

    Roosevelt Power July Impact

    Comments (-1)
  • Roosevelt Monthly Construction Update

    Posted by Neta Miller on 6/7/2019 7:05:00 AM

    Construction Update: June 2019

    Project: Interim Housing

    Construction Update: In May, the interim housing scope was bid and awarded.

    One Month Look Ahead: In June, construction is expected to include preparation of building pads, the delivery of six interim housing portables, and accessibility ramp attachment. Electrical work to connect the portables to power and data is also expected to begin.

    Immediate Impacts:
    Roosevelt June Impacts

    Comments (-1)
  • Roosevelt April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 PM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more educational opportunities for the future leaders of our community.

     

    In the 2017-18 school year, the Roosevelt School Modernization project went through Schematic Design, Design Development, and Construction Document phases.

     

    The Roosevelt Modernization project has, as of February 2019, been submitted to the Division of the State Architect (DSA). DSA is a government body that provides design and construction oversight for K-12 schools, and will review Roosevelt’s Modernization Construction Documents for compliance and accessibility.

     

    The scope of work submitted to DSA for Roosevelt Modernization includes, and is not limited to, the following:

    • New lunch shelter
    • New kitchen equipment
    • Updated storm water drainage system
    • Modernize existing restrooms
    • New concrete walkways
    • Exterior patch and paint
    • Selective flooring
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Fire alarm system upgrades
    • Security camera installation
    • Upgrade It data wiring
    • Classroom technology package (includes Redcat Access classroom voice enhancement system)

     

    All scope is subject to change. The Roosevelt Modernization project is expected to complete DSA review in Fall 2019.

     

    Roosevelt will additionally complete a Solar Panel project. Construction for the Solar Panel project is currently expected to begin in June 2019 and to be completed by October 2019, dates subject to change.

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.