    Welcome to the North Star Academy Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by Spencer Associates with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     Progress Timeline
  • North Star Monthly Construction Updates

    Posted by Neta Miller on 3/5/2020 8:20:00 AM

    Update: March 2019

     

    Project: Modernization

     

    Construction Update: In February, fencing installation was completed.

     

    One Month Look Ahead: In March, the project will be substantially completed.

    Comments (-1)
  • North Star Monthly Construction Update

    Posted by Neta Miller on 2/5/2020 7:05:00 AM

    Update: February 2019

    Project: Modernization

    Construction Update: In January, fencing installation continued.

    One Month Look Ahead: In February, fencing installation is expected to be completed and the project will be substantially completed.

    Comments (-1)
  • North Star Modernization Construction Monthly Update

    Posted by Neta Miller on 1/9/2020 1:05:00 PM

    Update: December 2019

    Project: Modernization

    Construction Update: In December, door hardware and fencing installation continued.

    One Month Look Ahead: In January, the project is expected to be completed.

    Comments (-1)
  • North Star Monthly Construction Update

    Posted by Neta Miller on 12/6/2019 3:10:00 PM

    Update: December 2019

     

    Project: Modernization

    Construction Update: In November, project progressed on schedule

    One Month Look Ahead: In December, door hardware and fencing installation will continue, and the project is expected to be complete of the Winter break.

    Comments (-1)
  • North Star Monthly Construction Update

    Posted by Neta Miller on 11/5/2019 3:05:00 PM

    Update: November 2019

    Project: Modernization

    Construction Update: In October, door hardware installation, fence and gate installation, and punch list items continued.

    One Month Look Ahead: In November, door hardware installation, fence and gate installation, and punch list items will continue.

    Comments (-1)
  • North Star Monthly Construction Update

    Posted by Neta Miller on 10/10/2019 3:00:00 PM

    Update: October 2019

    Project: Modernization

    Construction Update: In September, ADA handrail installation, door hardware installation, fence and gate installation, and punch list items continued.

    One Month Look Ahead: In October, handrail installation, door hardware installation, and fence and gate installation are expected to be completed. Punch list items will continue.

    Comments (-1)
  • North Star Summer 2019 Update

    Posted by Neta Miller on 9/12/2019 3:20:00 PM

    Welcome back to another beautiful school year! The Bond Team has been busy all summer, bringing the Measure T Bond Measure to life. From construction to design progress, the Bond Program is well on its way to transform and modernize the Redwood City School District.

     

    This summer, the district was full of construction:

    • 30 interim housing units were installed for use at the start of the 2019/20 school year
    • Eleven schools had active construction on their campus
    • Five school Modernization projects mobilized
    • Four solar projects mobilized
    • Four Electric Vehicle Charging projects mobilized

     

    North Star Academy Modernization saw the following progress:

    • Restroom upgrades completed
    • Asphalt and paving completed
    • Curb ramp completed
    • New signage completed
    • Door hardware upgrades began

     

    The District and the Bond Team look forward to continued progress on campus and across the district, and to serving our community. Everyone is working hard to make the Redwood City School District the best learning environment it can be!

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • North Star Construction Update

    Posted by Neta Miller on 9/4/2019 7:05:00 AM

    Update: September 2019

    Project: Modernization

    Construction Update: In August, restroom upgrades, asphalt paving, improved curb ramp, and signage were completed.

    One Month Look Ahead: In September, door hardware, fencing, gate, and handrail installation will continue, along with punch list items.

    Comments (-1)
  • North Star Monthly Construction Update July

    Posted by Karen Summerville on 7/5/2019 7:00:00 AM

    Construction Update: July 2019

    Project: Modernization

    Construction Update: In June, the layouts for curb ramps around building F began. 

    One Month Look Ahead: In July, site work will begin, including curve ramp demolition and reconstruction around building F, upgrading drinking fountains, retrofitting handrails, restroom reconfiguration in the staff bathroom.  Additionally, gate and fencing installation will begin.

    Immediate Impacts:

    North Star Sound Water After Hours Weekend July Impacts

    Comments (-1)
  • North Star April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 AM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more education opportunities for the future leaders of our community.

     

    In 2017-18 North Star Academy received a new lunch shelter, and the Modernization project went through Schematic Design, Design Development, and Construction Document phases.

     

    The North Star Modernization project is currently under construction. Construction is expected to be completed by the start of the 2019-20 school year.

     

    The scope of work currently under construction includes:

    • New concrete walkways
    • Slurry coat and stripe existing paving
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Security camera installation
    • Classroom technology package (includes Redcat Access classroom voice enhancement system and flat screen TVs on motorized, adjustable carts)

     

    All scope is subject to change.

     

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.