•  MIT
     
     
    Program Management Team: Brailsford and Dunlavey | RGMK & AssociatesB&D      RGM   
     
    Status: Construction
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the McKinley Institute of Technology Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by Spencer Associates with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     Progress Timeline
  • McKinley Monthly Construction Update

    Posted by Neta Miller on 3/5/2020 7:35:00 AM

    Update: March 2019

     

    Project: Modernization

     

    Construction Update: In February, fencing installation was completed.

     

    One Month Look Ahead: In March, the project will be substantially completed.

    Comments (-1)
  • McKinley Monthly Construction Update

    Posted by Neta Miller on 2/5/2020 7:10:00 AM

    Update: February 2019

    Project: Modernization

    Construction Update: In January, fencing installation continued.

    One Month Look Ahead: In February, fencing installation is expected to be completed and the project will be substantially completed.

    Comments (-1)
  • McKinley Modernization Monthly Construction Update

    Posted by Neta Miller on 1/9/2020 1:00:00 PM

    Update: December 2019

    Project: Modernization

    Construction Update: In December, door hardware and fencing installation continued.

    One Month Look Ahead: In January, the project is expected to be completed.

    Comments (-1)
  • McKinley Monthly Construction Update

    Posted by Neta Miller on 12/6/2019 4:10:00 PM

    Update: December 2019

     

    Project: Modernization

    Construction Update: In November, project progressed on schedule

    One Month Look Ahead: In December, door hardware and fencing installation will continue, and the project is expected to be complete of the Winter break.

    Comments (-1)
  • McKinley Monthly Construction Update

    Posted by Neta Miller on 11/5/2019 3:10:00 PM

    Update: November 2019

    Project: Modernization

    Construction Update: In October, door hardware installation, fence and gate installation, and punch list items continued.

    One Month Look Ahead: In November, door hardware installation, fence and gate installation, and punch list items will continue.

    Comments (-1)
  • McKinley Monthly Construction Update

    Posted by Neta Miller on 10/10/2019 3:00:00 PM

    Update: October 2019

    Project: Modernization

    Construction Update: In September, ADA stair handrail installation was completed. Door hardware installation, fence and gate installation, and punch list items continued.

    One Month Look Ahead: In October, door hardware installation, fence and gate installation, and punch list items will continue.

    Comments (-1)
  • McKinley Summer 2019 Update

    Posted by Neta Miller on 9/12/2019 3:15:00 PM

    Welcome back to another beautiful school year! The Bond Team has been busy all summer, bringing the Measure T Bond Measure to life. From construction to design progress, the Bond Program is well on its way to transform and modernize the Redwood City School District.

     

    This summer, the district was full of construction:

    • 30 interim housing units were installed for use at the start of the 2019/20 school year
    • Eleven schools had active construction on their campus
    • Five school Modernization projects mobilized
    • Four solar projects mobilized
    • Four Electric Vehicle Charging projects mobilized

     

    McKinley Institute of Technology Modernization saw the following progress:

    • Drinking fountain installation completed
    • Electrical upgrades completed
    • ADA ramps installed
    • Door hardware upgrades began
    • Fencing and gate installation began
    • ADA stair handrail installation began

     

    McKinley Ramp  

    The District and the Bond Team look forward to continued progress on campus and across the district, and to serving our community. Everyone is working hard to make the Redwood City School District the best learning environment it can be!

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • McKinley Modernization Monthly Construction Update

    Posted by Neta Miller on 9/4/2019 7:00:00 AM

    Update: September 2019

    Project: Modernization

    Construction Update: In August, drinking fountain installation, electrical work, and ADA ramp work was completed.

    One Month Look Ahead: In September, door hardware, fence, gate, and ADA stair handrail installation will continue, along with the punch list items.

    Comments (-1)
  • McKinley Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 7:00:00 AM

    McKinley Progress Photo


    McKinley Progress Photo

     

    Update: August 2019

    Project: Modernization

    Construction Update: In July interior electrical work and exterior stair installation continued and ADA and drinking fountain scopes began.

    One Month Look Ahead: In August, ADA scope, asphalt paving, drinking fountain installation, and interior electrical work will be completed. Signage work will begin, along with fencing and door scopes, and the final IT inspection of electrical work will be conducted.

    Immediate Impacts:
    McKinley August Impacts: Traffic, Sound, After Hours, Weekend

    Comments (-1)
  • McKinley Monthly Construction Update July

    Posted by Neta Miller on 7/5/2019 7:00:00 AM

    McKinley July Progress

    Construction Update: July 2019

    Project: Modernization

    Construction Update: In June, steel installation of the exterior stairs began, as well as the moderinzation of the administrative office spaces. 

    One Month Look Ahead: In July, the interior electrical work modernization is expected to be completed, and the exterior stair installation will be completed. 

    Immediate Impacts:

    McKinley Traffic Sound After Hours Weekend July Impacts

    Comments (-1)