•  Kennedy
     
     
    Program Management Team: Brailsford and Dunlavey | RGM & AssociatesB&D      RGM   
     
    Status: Schematic Design
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the John F. Kennedy Middle School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     1039

     
  • Kennedy Administration Building and Parking Lot Monthly Update

    Posted by Neta Assaf on 3/1/2019 6:00:00 AM

    Construction Update: March 2019

    Project: New Administration Building and Parking Lot

    Construction Update: Last month,  grading for the new administration building was completed, and the project receive dthe building pad certification and began utility trenching.

     

    One Month Look Ahead: In March, grade and basercock will be finished, and trenching for underground utilities will continue. Footing layout, excavation, and rebar will begin and finish in March, as will the footing concrete placement. 

    Immediate Impacts

    JFK March

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Weekly Update

    Posted by Neta Assaf on 2/18/2019 6:00:00 AM

     Weekly Construction Update: Week of February 18, 2019

    Project: New Administration Building and Parking Lot

    Construction Update: Last week, continued digging of trenches for underground utilities, which was extended due to rain

     

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, weather permitting. Will be followed by new administration building footing layout

    Immediate Impacts

    JFK Construction Impacts

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Weekly Update

    Posted by Neta Assaf on 2/11/2019 7:00:00 AM

     Weekly Construction Update: Week of February 11, 2019

    Project: New Administration Building and Parking Lot

    Description of Work: New Administration building pad and grading complete, and continued digging of trenches for underground utilities.

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, compaction, and grading of the site, weather permitting.

    Immediate Impacts

    JFK 190211

    Comments (-1)
  • Kennedy Construction Weekly Update

    Posted by Neta Assaf on 2/1/2019 7:00:00 AM

     Weekly Construction Update: Week of February 4, 2019

    Project: New Administration Building and Parking Lot

    Description of Work: Site grading, compaction, and certification of New Administration Building Pad. Continued underground utilities trenching delayed due to weather

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, compaction, and grading of the site, weather permitting.

    Immediate Impacts

    Impacts JFK

     

    JFK Photo

     

    Comments (-1)
  • Kennedy Design Update

    Posted by Neta Assaf on 9/30/2018 6:00:00 AM

    Another summer full of fun (and work) has come and gone at John. F Kennedy Middle School! Welcome back, we hope your school year is successful. The Bond Team is propelling the Measure T Bond Measure’s vision into reality. The design and construction process is being carefully guided, with everyone focused on making the Redwood City School District (RCSD) the best place for learning and exploration it can be.

     

    Kennedy has already seen the completion of a new double bay lunch enclosure with benches in November 2017.

     

    This summer, Kennedy has been full of activity:

    • A Construction-Related Testing and Inspection Agreement with Ninyo and Moore was approved by the Board.
    • A Construction Management Consultant Agreement with Roebbelen for Kennedy’s administration building and parking lot projects is being finalized.
    • The team received Design Development for Kennedy Modernization, which expands on Schematic Design, finalizing the design, specific building materials, and engages additional design experts (i.e. structural, mechanical, and landscape engineers).
    • The team is in the Construction Documents phase for Kennedy Modernization, which produces drawing with greater detail that will be used during construction.
    • The Kennedy Administration and Family Center project has been submitted and approved by DSA.
    • Bid were received for the Kennedy Administration and Family Center project on October 2, 2018.

     

    Next steps for the Kennedy Modernization project include concluding the Construction Documents phase, followed by submission to the Division of the State Architect (DSA). Once DSA sign off has been received, the Kennedy Modernization project will go into the bidding and construction phases.

     

    The Kennedy Administration and Family Center project is awaiting review and sign off from DSA, which will be followed by the bidding and construction phases.

     

    The Bond Team is happy to share that the timeline for completing all RCSD school site projects has been shortened to five years instead of the previously expected seven. Construction on some District sites is expected to begin as early as the start of 2019.

     

    For further information and inquiry, please contact Don Dias.

    Comments (-1)
  • Kennedy Lunch Shelter Weekly Update

    Posted by Ty Specht on 11/6/2017 7:00:00 AM

    Weekly Construction Update: Week of November 6

    Project: Lunch Shelter

    Description of Work: General Contractor has removed all of the dirt and debris on site.  Installed drainage pipes and connected to the city's Storm Water pipes.  Shade Structure installer has completed the concrete footings, set steel plates, steel columns, and grout.

    One Week Schedule: General Contractor to touch up asphalt pavement? and site landscaping.

    Immediate Site Impacts:

      Y N   Nature of Impact      
    Traffic   X    
    Sound     Trucks and pouring.
    Smell   X    
    Power   X    
    Classroom Impact   X    
    After Hours work   X    
    Weekend Work   X    
    Weather Delay   X    

    JFK1  

    JFK2

    JFK3

    Comments (-1)
  • Kennedy Lunch Shelter Weekly Update

    Posted by Ty Specht on 10/30/2017

    Weekly Construction Update: Week of October 30 - November 3

    Project: Lunch Shelter

    Description of Work: Forms have been placed for the asphalt.  Rebar cages have been delivered to the site.  Drilling has been completed for the placement of the cages. Site tables and benches have been delivered to the site.

    One Week Schedule: Concrete pour to occur and Shade structure installation to be initiated.

    Immediate Site Impacts:

      Y N   Nature of Impact      
    Traffic   X    
    Sound X     Loud demolition and heavy equipment noise.
    Smell   X    
    Power   X    
    Classroom Impact X     Minimal, site is adjacent to the exterior play areas.
    After Hours work   X    
    Weekend Work   X    
    Weather Delay   X    

     

    Comments (-1)
  • Kennedy Lunch Shelter Weekly Update

    Posted by Ty Specht on 10/23/2017 11:50:00 AM

    Weekly Construction Update: Week of October 23-27

    Project: Lunch Shelter

    Description of Work: Construction company completed the removal of existing landscape.  Other work included removal and installation of underground utilities to include sewer, electrical, and irrigation. All site demolition and ground leveling has been completed.  The construction company also planted new trees. 

    One Week Schedule: The construction company will continue installing the irrigation system. The first metal pieces of the Lunch Shelter will be delivered and installed.

    Immediate Site Impacts:

      Y N   Nature of Impact      
    Traffic   X    
    Sound X     Loud demolition and heavy equipment noise.
    Smell   X    
    Power   X    
    Classroom Impact X     Minimal, site is adjacent to the exterior play areas.
    After Hours work   X    
    Weekend Work   X    
    Weather Delay   X    

     JFK Lunch Shelter

    Comments (-1)
  • Kennedy Lunch Shelter Schedule Update

    Posted by Ty Specht on 8/22/2017 12:00:00 PM

    To the Communities of Fair Oaks, Roy Cloud, John F. Kennedy, North Star Academy, and MIT Schools,

     

    The Bond Program Team would like to update you on the progress of the Lunch Shelter Projects scheduled to start this summer while the students were on break.

     

    We are equally disappointed the lunch shelters are not installed but State of California Regulations sometimes slow projects down, as they did in this case. These regulations are in place to ensure the absolute safety of students and staff and provide the oversite for all safety on State Property. I appreciate these checks and balances as nothing is more important than the safety of our students.

     

    The California Geological Survey (CGS), working in partnership with the Division of State Architects (DSA), identified issues with the soil in "liquefaction zones" at some of our sites that require additional design review, hence the delay in approval at those identified sites and where we are today.

     

    The Bond Team negotiated a large purchase discount by agreeing to install all five shelters at the same time. We agreed this to ensure all five projects meet the budget. All shelters will be shipped to the schools when final design approval is granted for all sites. There is a Special Inspector assigned to this manufacturing plant that oversaw the construction to ensure all welds are properly performed on these structures during the entire production process.

     

    We will have two different Contractors performing the on-site work, the first does all the ground preparation and accessibility update requirements and the second installs the actual structures.

     

    Next step is awarding a contractor to complete the ground work. Bid opening is on August 24. Unfortunately, no contractors bid on this project during the first solicitation over the summer citing their summer schedules were full. Once on-site, this contractor will be required to fence off the area of work to physically separate the students from the construction for safety.

     

    Following that, the structures will be delivered and installed. With the lunch shelters in place, the final ground work will be completed and then picnic tables will be installed. We appreciate your patience with this process. We know it is disappointing, but student safety must never be compromised for the sake of a paper or verbal schedule.

     

    Regards,

     

    The Measure T Bond Program Team

    Comments (-1)
  • Kennedy Conceptual Design

    Posted by Ty Specht on 8/17/2017 9:45:00 AM

    There are multiple phases of design that your school will progress through over the next several month. Those phases include:

     

    • Conceptual Design
    • Schematic Design
    • Design Development
    • Construction Documents
    •  

    A critical part of every project is the budget and ensuring that the design maximizes the budget. The architect of your school was provided a set budget and a design objective based on the goals of the Master Facility Plan and the board approved Gap Analysis finding. The attached document reflects the architect’s conceptual design for your site. Conceptual designs can be considered the first drawings that outline desires and opportunities. The level of detail is limited in this phase. The next phase, schematic development, will show addition details like wall locations, doors, and windows.

     

    The Bond Program Team is in constant contact with the school principal to confirm design developments through the entire process for feedback and design confirmation.

     

    Conceptual Design

    Comments (-1)