•  Kennedy
     
     
    Program Management Team: Brailsford and Dunlavey | RGMK & AssociatesB&D      RGM   
     
    Status: Construction
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the John F. Kennedy Middle School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     1039

     
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 11/5/2019 3:05:00 PM

    Update: November 2019

     

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In September, wall insulation installation, gyp board installation, rough HVAC, rough electrical, and window and door system installation were all completed. Ceramic tiles were also installed.

    One Month Look Ahead: In October, plaster will be applied, and interior painting, epoxy flooring, canopy framing, and plumbing are expected to be completed.

     

    Project (2 of 2): Electric Vehicle Charging Stations

    Construction Update: In October, this project was completed.

    One Month Look Ahead: In November, this project will be in closeout.

     

    Project (3 of 3): Modernization

    Construction Update: Project is currently bidding, and construction will begin after November.

    Comments (-1)
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 10/10/2019 3:00:00 PM

    Update: October 2019

     

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In September, wall insulation installation, gyp board installation, rough HVAC, rough electrical, and window and door system installation were all completed. Ceramic tiles were also installed.

    One Month Look Ahead: In October, plaster will be applied, and interior painting, epoxy flooring, canopy framing, and plumbing are expected to be completed.

     

    Project (2 of 3): Interim Housing Portables

    Construction Update: The interim housing portables are in full use.

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In September, installation began.

    One Month Look Ahead: In October, installation will continue.

     

    Kennedy Admin September Progress

     

    Kennedy Admin September Progress

    Comments (-1)
  • Kennedy Summer 2019 Update

    Posted by Neta Miller on 9/12/2019 3:20:00 PM

    Welcome back to another beautiful school year! The Bond Team has been busy all summer, bringing the Measure T Bond Measure to life. From construction to design progress, the Bond Program is well on its way to transform and modernize the Redwood City School District.

     

    This summer, the district was full of construction:

    • 30 interim housing units were installed for use at the start of the 2019/20 school year
    • Eleven schools had active construction on their campus
    • Five school Modernization projects mobilized
    • Four solar projects mobilized
    • Four Electric Vehicle Charging projects mobilized

     

    John F. Kennedy Middle School saw the following progress:

    • The new one-story Administration Building
      • Building rough framing completed
      • Bio retention completed
      • Rough electrical for walls completed
      • Rough plumbing completed
      • Door frames installed
      • Roofing installed
    • Parking lot is 85% complete
    • Four Interim Housing Units installed
    • All Interim Housing Units were connected for power and data
    • Electric Vehicle Charging station infrastructure substantially completed
    • Electric Vehicle Charger installation began

     

    Kennedy New Admin Building

     

    Kennedy Parking Lot

     

    The District and the Bond Team look forward to continued progress on campus and across the district, and to serving our community. Everyone is working hard to make the Redwood City School District the best learning environment it can be!

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Kennedy Construction Weekly Update

    Posted by Neta Miller on 9/4/2019 7:05:00 AM

    Update: September 2019

     

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In August, concrete placement, paving, and stripping at the parking lot were completed. At the New Administration building, bio-retention work, rough framing, rough electrical, plumbing, roof insulation and roofing, and door frame installation work all continued.

    One Month Look Ahead: In September, rough HVAC, electrical, wall insulation, and exterior plaster will begin, along with interior and exterior painting.

     

    Project (2 of 3): Interim Housing Portables

    Construction Update: In August, punch list item work began at the interim housing portables.

    One Month Look Ahead: In September, punch list items will be completed for the interim housing

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In August, infrastructure and concrete bases were completed.

    One Month Look Ahead: In September, installation of the charger will begin.

    Comments (-1)
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 7:05:00 AM

    JFK Progress Photo


    JFK Progress Photo


    JFK Progress Photo

     

    Update: August 2019

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In July rough wood framing and bio-retention excavation continued, and rough utilities began.

    One Month Look Ahead: In August the rough utilities work, bio-retention area work, and the new drop off area will be completed.


    Project (2 of 3): Interim Housing

    Construction Update: In July the interim housing portables were connected to power and overhead cabling began.

    One Month Look Ahead: In August overhead cabling will continue and the punch list work will begin.

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In July, infrastructure setting began and was substantially completed. 

    One Month Look Ahead: The project is on track for completion by the end of August.

     

    Immediate Impacts:
    JFK Traffic and Sound Impacts in August

    Comments (-1)
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 7/5/2019 7:00:00 AM

    Kennedy July Progress

    Kennedy July Progress


    Kennedy July Progress


    Kennedy July Progress

     

    Construction Update: July 2019

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In June, rough wood framing of the new administration building continued and bio-retention excavation and placement began.

    One Month Look Ahead: In July, rough wood framing and bio-retention will continue. Electrical, plumbing, and mechanical system installations will begin.

     

     

    Project (2 of 3): Interim Housing

    Construction Update: In June, electrical work to connect the portables to power and data began.

    One Month Look Ahead: In July, electrical work is expected to be completed, including overhead cabling. 

     

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In June, the project was mobilized with the expectation of completion by the start of the 2019/20 school year. 

    One Month Look Ahead: In July, infrastructures setting began, and the project is on track for completion in July.

     

    Impacts

    Kennedy Traffic Sound Power July Impacts

    Comments (-1)
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 6/7/2019 7:00:00 AM

    Construction Update: June 2019

    Project (1 of 2): New Administration Building and Parking Lot

    Construction Update: In May, concrete slab-on-grade was placed, rough wood framing began, and site work associated with the new drop off area began.

    One Month Look Ahead: In June, rough wood framing will continue, bio-retention excavation and placement will begin.

     

    Project (2 of 2): Interim Housing

    Construction Update: In May, four portables were delivered and accessibility ramps attached.

    One Month Look Ahead: In June, construction is expected to include the start of electrical work to connect the portables to power and data.

     

    Immediate Impacts:
    Kennedy June  Impacts

    Comments (-1)
  • Kennedy April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 AM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more educational opportunities for the future leaders of our community.

     

    In 2017-18 Kennedy Middle School received a new lunch shelter, and the Modernization project went through Schematic Design, Design Development, and Construction Document phases.

     

    The Kennedy Administration Building and Parking Lot project is currently under construction, and is expected to be completed by the end of 2019.

     

    The scope of work currently under construction includes:

    • New administration building and family center
    • Relocate existing underground utilities
    • Science labs
    • Modernize existing classrooms
    • Update storm water drainage system
    • New kitchen equipment
    • New parking lot and concrete walkways
    • New drop-off/bus loop area
    • Slurry coat and stripe existing paving
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Security camera installation
    • Classroom technology package (includes Redcat Access classroom voice enhancement system and flat screen TVs on motorized, adjustable carts)

    All scope is subject to change.

     

    Kennedy will additionally complete an Electric Vehicle (EV) Charging Stations project. The EV Charging Stations design is currently 50% complete.

     

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.

     

    JFK April Update

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Monthly Update

    Posted by Neta Assaf on 3/1/2019 6:00:00 AM

    Construction Update: March 2019

    Project: New Administration Building and Parking Lot

     

    Construction Update: Last month, grading for the new administration building was completed, and the project received the building pad certification and began utility trenching.

     

    One Month Look Ahead: In March, grade and basercock will be finished, and trenching for underground utilities will continue. Footing layout, excavation, and rebar will begin and finish in March, as will the footing concrete placement. 

    Immediate Impacts

    JFK March

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Weekly Update

    Posted by Neta Assaf on 2/18/2019 6:00:00 AM

     Weekly Construction Update: Week of February 18, 2019

    Project: New Administration Building and Parking Lot

    Construction Update: Last week, continued digging of trenches for underground utilities, which was extended due to rain

     

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, weather permitting. Will be followed by new administration building footing layout

    Immediate Impacts

    JFK Construction Impacts

    Comments (-1)