•  Kennedy
     
     
    Program Management Team: Brailsford and Dunlavey | RGM & AssociatesB&D      RGM   
     
    Status: Construction
    Contact Us: Don Dias
     
     
     
     
    Other Project Details: 
     

    Welcome to the John F. Kennedy Middle School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by DLM-HED Architecture with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     1039

     
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 7:05:00 AM

    JFK Progress Photo


    JFK Progress Photo


    JFK Progress Photo

     

    Update: August 2019

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In July rough wood framing and bio-retention excavation continued, and rough utilities began.

    One Month Look Ahead: In August the rough utilities work, bio-retention area work, and the new drop off area will be completed.


    Project (2 of 3): Interim Housing

    Construction Update: In July the interim housing portables were connected to power and overhead cabling began.

    One Month Look Ahead: In August overhead cabling will continue and the punch list work will begin.

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In July, infrastructure setting began and was substantially completed. 

    One Month Look Ahead: The project is on track for completion by the end of August.

     

    Immediate Impacts:
    JFK Traffic and Sound Impacts in August

    Comments (-1)
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 7/5/2019 7:00:00 AM

    Kennedy July Progress

    Kennedy July Progress


    Kennedy July Progress


    Kennedy July Progress

     

    Construction Update: July 2019

    Project (1 of 3): New Administration Building and Parking Lot

    Construction Update: In June, rough wood framing of the new administration building continued and bio-retention excavation and placement began.

    One Month Look Ahead: In July, rough wood framing and bio-retention will continue. Electrical, plumbing, and mechanical system installations will begin.

     

     

    Project (2 of 3): Interim Housing

    Construction Update: In June, electrical work to connect the portables to power and data began.

    One Month Look Ahead: In July, electrical work is expected to be completed, including overhead cabling. 

     

     

    Project (3 of 3): Electric Vehicle Charging Stations

    Construction Update: In June, the project was mobilized with the expectation of completion by the start of the 2019/20 school year. 

    One Month Look Ahead: In July, infrastructures setting began, and the project is on track for completion in July.

     

    Impacts

    Kennedy Traffic Sound Power July Impacts

    Comments (-1)
  • Kennedy Monthly Construction Update

    Posted by Neta Miller on 6/7/2019 7:00:00 AM

    Construction Update: June 2019

    Project (1 of 2): New Administration Building and Parking Lot

    Construction Update: In May, concrete slab-on-grade was placed, rough wood framing began, and site work associated with the new drop off area began.

    One Month Look Ahead: In June, rough wood framing will continue, bio-retention excavation and placement will begin.

     

    Project (2 of 2): Interim Housing

    Construction Update: In May, four portables were delivered and accessibility ramps attached.

    One Month Look Ahead: In June, construction is expected to include the start of electrical work to connect the portables to power and data.

     

    Immediate Impacts:
    Kennedy June  Impacts

    Comments (-1)
  • Kennedy April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 AM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more educational opportunities for the future leaders of our community.

     

    In 2017-18 Kennedy Middle School received a new lunch shelter, and the Modernization project went through Schematic Design, Design Development, and Construction Document phases.

     

    The Kennedy Administration Building and Parking Lot project is currently under construction, and is expected to be completed by the end of 2019.

     

    The scope of work currently under construction includes:

    • New administration building and family center
    • Relocate existing underground utilities
    • Science labs
    • Modernize existing classrooms
    • Update storm water drainage system
    • New kitchen equipment
    • New parking lot and concrete walkways
    • New drop-off/bus loop area
    • Slurry coat and stripe existing paving
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Security camera installation
    • Classroom technology package (includes Redcat Access classroom voice enhancement system and flat screen TVs on motorized, adjustable carts)

    All scope is subject to change.

     

    Kennedy will additionally complete an Electric Vehicle (EV) Charging Stations project. The EV Charging Stations design is currently 50% complete.

     

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.

     

    JFK April Update

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Monthly Update

    Posted by Neta Assaf on 3/1/2019 6:00:00 AM

    Construction Update: March 2019

    Project: New Administration Building and Parking Lot

     

    Construction Update: Last month, grading for the new administration building was completed, and the project received the building pad certification and began utility trenching.

     

    One Month Look Ahead: In March, grade and basercock will be finished, and trenching for underground utilities will continue. Footing layout, excavation, and rebar will begin and finish in March, as will the footing concrete placement. 

    Immediate Impacts

    JFK March

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Weekly Update

    Posted by Neta Assaf on 2/18/2019 6:00:00 AM

     Weekly Construction Update: Week of February 18, 2019

    Project: New Administration Building and Parking Lot

    Construction Update: Last week, continued digging of trenches for underground utilities, which was extended due to rain

     

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, weather permitting. Will be followed by new administration building footing layout

    Immediate Impacts

    JFK Construction Impacts

    Comments (-1)
  • Kennedy Administration Building and Parking Lot Weekly Update

    Posted by Neta Assaf on 2/11/2019 7:00:00 AM

     Weekly Construction Update: Week of February 11, 2019

    Project: New Administration Building and Parking Lot

    Description of Work: New Administration building pad and grading complete, and continued digging of trenches for underground utilities.

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, compaction, and grading of the site, weather permitting.

    Immediate Impacts

    JFK 190211

    Comments (-1)
  • Kennedy Construction Weekly Update

    Posted by Neta Assaf on 2/1/2019 7:00:00 AM

     Weekly Construction Update: Week of February 4, 2019

    Project: New Administration Building and Parking Lot

    Description of Work: Site grading, compaction, and certification of New Administration Building Pad. Continued underground utilities trenching delayed due to weather

    One Week Look Ahead: General Contractor to continue digging the underground utility trenches, compaction, and grading of the site, weather permitting.

    Immediate Impacts

    Impacts JFK

     

    JFK Photo

     

    Comments (-1)
  • Kennedy Design Update

    Posted by Neta Assaf on 9/30/2018 6:00:00 AM

    Another summer full of fun (and work) has come and gone at John. F Kennedy Middle School! Welcome back, we hope your school year is successful. The Bond Team is propelling the Measure T Bond Measure’s vision into reality. The design and construction process is being carefully guided, with everyone focused on making the Redwood City School District (RCSD) the best place for learning and exploration it can be.

     

    Kennedy has already seen the completion of a new double bay lunch enclosure with benches in November 2017.

     

    This summer, Kennedy has been full of activity:

    • A Construction-Related Testing and Inspection Agreement with Ninyo and Moore was approved by the Board.
    • A Construction Management Consultant Agreement with Roebbelen for Kennedy’s administration building and parking lot projects is being finalized.
    • The team received Design Development for Kennedy Modernization, which expands on Schematic Design, finalizing the design, specific building materials, and engages additional design experts (i.e. structural, mechanical, and landscape engineers).
    • The team is in the Construction Documents phase for Kennedy Modernization, which produces drawing with greater detail that will be used during construction.
    • The Kennedy Administration and Family Center project has been submitted and approved by DSA.
    • Bid were received for the Kennedy Administration and Family Center project on October 2, 2018.

     

    Next steps for the Kennedy Modernization project include concluding the Construction Documents phase, followed by submission to the Division of the State Architect (DSA). Once DSA sign off has been received, the Kennedy Modernization project will go into the bidding and construction phases.

     

    The Kennedy Administration and Family Center project is awaiting review and sign off from DSA, which will be followed by the bidding and construction phases.

     

    The Bond Team is happy to share that the timeline for completing all RCSD school site projects has been shortened to five years instead of the previously expected seven. Construction on some District sites is expected to begin as early as the start of 2019.

     

    For further information and inquiry, please contact Don Dias.

    Comments (-1)
  • Kennedy Lunch Shelter Weekly Update

    Posted by Ty Specht on 11/6/2017 7:00:00 AM

    Weekly Construction Update: Week of November 6

    Project: Lunch Shelter

    Description of Work: General Contractor has removed all of the dirt and debris on site.  Installed drainage pipes and connected to the city's Storm Water pipes.  Shade Structure installer has completed the concrete footings, set steel plates, steel columns, and grout.

    One Week Schedule: General Contractor to touch up asphalt pavement? and site landscaping.

    Immediate Site Impacts:

      Y N   Nature of Impact      
    Traffic   X    
    Sound     Trucks and pouring.
    Smell   X    
    Power   X    
    Classroom Impact   X    
    After Hours work   X    
    Weekend Work   X    
    Weather Delay   X    

    JFK1  

    JFK2

    JFK3

    Comments (-1)