    Welcome to the Henry Ford Elementary School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by CSDA Design Group with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

     

     Progress Map

     
  • Henry Ford Monthly Construction Update

    Posted by Neta Miller on 11/5/2019 3:00:00 PM

    Update: November 2019

    Project: Modernization

    Construction Update: Project is currently bidding, and construction will begin after November.

    Comments (-1)
  • Henry Ford Monthly Construction Update

    Posted by Neta Miller on 10/10/2019 3:00:00 PM

    Update: October 2019

    Project: Interim Housing

    Construction Update: The interim housing portables are in full use.

     

    Henry Ford Interim Housing September

    Comments (-1)
  • Henry Ford Summer Update

    Posted by Neta Miller on 9/12/2019 3:10:00 PM

    Welcome back to another beautiful school year! The Bond Team has been busy all summer, bringing the Measure T Bond Measure to life. From construction to design progress, the Bond Program is well on its way to transform and modernize the Redwood City School District.

     

    This summer, the district was full of construction:

    • 30 interim housing units were installed for use at the start of the 2019/20 school year
    • Eleven schools had active construction on their campus
    • Five school Modernization projects mobilized
    • Four solar projects mobilized
    • Four Electric Vehicle Charging projects mobilized

     

    Henry Ford Elementary School saw the following progress:

    • One Interim Housing Unit installed
    • Interim Housing Unit was connected to power and data
    • New lunch structure and tables

     

    Currently, the Henry Ford Modernization scope is under review by the Division of the State Architect (DSA). DSA is a government body that provides design and construction oversight for K-12 school, and once the Bond Team receives DSA sign-off, procurement for construction will begin.

     

    The District and the Bond Team look forward to continued progress on campus and across the district, and to serving our community. Everyone is working hard to make the Redwood City School District the best learning environment it can be!

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Henry Ford Monthly Construction Update

    Posted by Neta Miller on 9/4/2019 7:00:00 AM

    Update: September 2019

    Project: Interim Housing

    Construction Update: In August, punch list item work began at the interim housing portables.

    One Month Look Ahead: In September, punch list items will be completed for the interim housing portables.

    Comments (-1)
  • Henry Ford Monthly Construction Update

    Posted by Neta Miller on 8/5/2019 7:05:00 AM

    Henry Ford Progress Photo

     

    Update: August 2019

    Project: Interim Housing

    Construction Update: In July, electrical work to connect the interim housing portables to power and data was completed.

    One Month Look Ahead: In August, punch list work will begin.

    Immediate Impacts:
    Henry Ford No Impacts August

    Comments (-1)
  • Henry Ford Monthly Construction Update July

    Posted by Karen Summerville on 7/5/2019 7:00:00 AM

    Construction Update: July 2019

    Project: Interim Housing

    Construction Update: In June, site work was completed, including preparation of building pads, delivery of interim housing portables, and asphalt grading for accessibility ramps. Electrical work to connect the portables to power and data began. 

    One Month Look Ahead: In July, electrical work to connect the portables to power and data will be completed.

    Immediate Impacts:

    Henry Ford Power July Impacts

    Comments (-1)
  • Henry Ford Monthly Construction Update

    Posted by Neta Miller on 6/7/2019 7:05:00 AM

    Construction Update: June 2019

    Project: Interim Housing

    Construction Update: In May, the interim housing scope was bid and awarded.

    One Month Look Ahead: In June, construction is expected to include preparation of building pads, the delivery of the interim housing portable, and grading of the asphalt accessibility ramp to begin and be completed.

    Immediate Impacts:
    Henry Ford June Impacts

    Comments (-1)
  • Henry Ford April Update

    Posted by Neta Assaf on 4/15/2019 7:00:00 AM

    This school year is gearing up to be an exciting one for Redwood City School District, and the Bond Team is looking forward to a year of continued progress for our schools as we work to bring more educational opportunities for the future leaders of our community.

     

    In the 2017-18 school year, the Henry Ford Elementary School Modernization project went through Schematic Design, Design Development, and Construction Document phases.

     

    The Henry Ford Modernization project has, as of November 2018, been submitted to the Division of the State Architect (DSA). DSA is a government body that provides design and construction oversight for K-12 schools, and will review Henry Ford’s Modernization Construction Documents for compliance and accessibility.

     

    The scope of work submitted to DSA for Henry Ford Modernization includes, and is not limited to, the following:

    • Reconfigure administration building
    • Reconfigure bus loop area
    • New kitchen equipment
    • Modernize existing restrooms
    • New lunch tables and umbrellas
    • New parking lot and concrete walkways
    • Slurry coat and stripe existing paving
    • HVAC system upgrades in the kitchen
    • Exterior patch and paint
    • Selective flooring
    • Updated safety locks for all classroom doors
    • Emergency response and wayfinding signage
    • Safety fencing and decorative gate
    • Security camera installation
    • Fire alarm system upgrades
    • Classroom technology package (includes Redcat Access classroom voice enhancement system and flat screen TVs on motorized, adjustable carts)

     

    All scope is subject to change. The Henry Ford Modernization project is expected to complete DSA review in Summer 2019.

     

    The Bond Team and the District are excited to see the progress being made to transform our schools into 21st century learning environments, and the progress and effect this Bond will have on our community.

     

    For further information or inquiry, please contact Don Dias.

    Comments (-1)
  • Henry Ford Design Update

    Posted by Neta Assaf on 8/30/2018 6:00:00 AM

    Another summer full of fun (and work) has come and gone at Henry Ford Elementary School! Welcome back, we hope your school year is successful. The Bond Team is propelling the Measure T Bond Measure’s vision into reality. The design and construction process is being carefully guided, with everyone focused on making the Redwood City School District (RCSD) the best place for learning and exploration it can be.

     

    This summer, Henry Ford has been full of activity:

    • A Construction-Related Testing and Inspection Agreement with Ninyo and Moore was approved by the Board.
    • The team received the Schematic Design set for Henry Ford, which determines the project requirements and goals.
    • The team received the Design Development set for Henry Ford, which expands on Schematic Design, finalizing the design, specific building materials, and engages additional design experts (i.e. structural, mechanical, and landscape engineers).
    • The team received the Construction Document set for Henry Ford, which produced drawings with greater detail that will be used during construction.

     

    The next steps for the Henry Ford include review and sign off from DSA, followed by the bidding and construction phases.

     

    The Bond Team is happy to share that the timeline for completing all RCSD school site projects has been shortened to five years instead of the previously expected seven. Construction on some District sites is expected to begin as early as the start of 2019.

     

    For further information and inquiry, please contact Don Dias.

    Comments (-1)
  • Henry Ford Conceptual Design

    Posted by Ty Specht on 8/17/2017 10:05:00 AM

    There are multiple phases of design that your school will progress through over the next several month. Those phases include:

     

    • Conceptual Design
    • Schematic Design
    • Design Development
    • Construction Documents
    •  

    A critical part of every project is the budget and ensuring that the design maximizes the budget. The architect of your school was provided a set budget and a design objective based on the goals of the Master Facility Plan and the board approved Gap Analysis finding. The attached document reflects the architect’s conceptual design for your site. Conceptual designs can be considered the first drawings that outline desires and opportunities. The level of detail is limited in this phase. The next phase, schematic development, will show addition details like wall locations, doors, and windows.

     

    The Bond Program Team is in constant contact with the school principal to confirm design developments through the entire process for feedback and design confirmation.

     