• Clifford Elementary School
     
    Program Management Team: Brailsford and Dunlavey | RGMK & AssociatesB&D      RGM   
     
    Status: Schematic Design
    Contact Us: Don Dias
     
     
      
    Other Project Details: 
     

    Welcome to the Clifford Elementary School Measure T Bond website. Below you will find periodic and important updates about your school. Over the next several months the Bond Program Team will present updates on the design and construction progress at your school. Your school is being designed by CSDA Design Group with support from your Site Council, Principal, Teachers, Staff, and local community.

     

    We thank you for your support of this bond and its associated projects.

    timeline

     

     

  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 5/31/2021

    Update: May 2021

    Project: Modernization

    Construction Update:  Compilation of necessary DSA forms to be uploaded to the agency’s server for review and comments.

    One Month Look Ahead: Pending DSA certification after review and payment of final invoice upon receipt by RCSD.

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 4/30/2021

    Update: April 2021

    Project: Modernization

    Construction Update:  Completion of Punchlist items and signed off by the Architect and Project Inspector. 

    One Month Look Ahead: Close-out process with the Division of State Architect.

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 3/31/2021

    Update: March 2021

    Project: Modernization

    Construction Update: Installation of fire access gate. Continue with miscellaneous punch list items.

    One Month Look Ahead: In April, completion of ADA access ramps and ADA path around building C.

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 2/26/2021

    Update: February 2021

    Project: Modernization

    Construction Update:  Punch list work in the garden area and miscellaneous items with door and door hardware.

    One Month Look Ahead: In March, continue with punch list and fire access gate installation.

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 1/27/2021

    Update: January 2021

    Project: Modernization

    Construction Update:  Installation of the perimeter ornamental and chain-link fences and gates are ongoing.

    One Month Look Ahead: In February, the contractor will be working on punch list items

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 12/30/2020

    Update: December 2020

    Project:  Modernization

    Construction Update:  Testing of the upgraded fire alarm system was completed and approved end of December 2020. Continued work in the Outdoor Learning Quad, installation of perimeter fencing, and installation of the walk-in cooler are projected for completion end of January.

    One Month Look Ahead: Completion of Outdoor Learning Quad and installation perimeter fencing.

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 11/25/2020

    Update: November 2020

    Project:  Modernization

    Construction Update:  Fire alarm scope and new FA panel installation begin in November and continue through the first week of December. Testing of the upgraded Fire Alarm system to occur during the second week of December.  Continued work in the Outdoor Learning Quad and perimeter fencing are both scheduled to be completed end of December.  Installation of the walk-in cooler will commence on the second week of December and is scheduled to be completed end of December.

    One Month Look Ahead: Continued work in the Outdoor Learning Quad, walk-in cooler, and perimeter fencing

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 10/28/2020

    Update: October 2020

    Project:  Modernization

    Construction Update:  Continue with Fire Alarm wire pull and installation at buildings B, C and D.  Replacement of water and sewer main lines are completed.  Continuing with fencing installation and installation of gates to follow

    One Month Look Ahead: Work on Fire Alarm upgrade, continue work in the Outdoor Garden Quad, perimeter fencing and walk-in cooler

    Comments (-1)
  • Clifford Monthly Construction Update

    Posted by Brittney Bennett on 9/30/2020

    Update: September 2020

    Project:  Modernization

    Construction Update:  Concrete pour for the ramps and seating walls at the Outdoor Learning Quad between buildings A and B to be completed. Completion of the Fire alarm conduit installations for Buildings A, B, and C. Work in the Library, Multi-Use Building, Building D East, and Building D West is ongoing.

    One Month Look Ahead: Continue with Fire Alarm upgrade scope, water and sewer line replacement and perimeter fencing

    Cliff1

     

    Cliff2

    Comments (-1)
  • Clifford Monthly Construction update

    Posted by Karen Summerville on 9/11/2020 12:00:00 PM

    Update: September 2020

    Welcome back to another beautiful school year. During the summer break, the project was approved by the Division of State Architect (DSA) to begin construction. The procurement/bid process was held over summer and a General Contractor was selected. The Board of Education also approved the General Contractor selected.

    Project (1 of 2): Solar

    Construction Update: This project was certified, and closeout is complete

    Project (2 of 2): Electric Vehicle Charging

    Construction Update: This project was certified, and closeout is complete.

    Project (3 of 3): Modernization

    Construction Update: General contractor mobilized, and Construction started in July.

    To date, the following scope items is ongoing: Flooring in 3 classrooms in A building is complete, site work, including concrete placement, storm drain installation, new fire alarm system, security door hardware installation, exterior painting, walk-in cooler installation, new ornamental fence, including gates.

    One Month Look Ahead: During the month of September and October, selective flooring in buildings B & C will be replaced, painting of building exterior continues, replacement of existing water line, and work will continue with the new outdoor learning area.